Completed -
The scheduled maintenance has been completed.
Sep 27, 18:00 BST
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Sep 27, 12:00 BST
Scheduled -
This are re-scheduled works from 20th September.
Compute datacenter in NY/NJ metro will be performing UPS-3 & UPS-4 MMS Startup and L4 Testing on 27th September 2025 between 07:00 and 13:00 EDT. During the works the primary power feed will not be available. The secondary feed is not going to be affected.
All Clouvider equipment is connected to both primary and secondary feeds, as such no power loss is expected during these works. Nevertheless the service should be considered at risk during these essential works.
Additionally, some servers are setup by their manufacturer to automatically clock down the CPU during a failure of one of the feeds. Customers utilising these servers will notice the CPU clock speed reduced while the feed is offline.
Clouvider will have enhanced engineering coverage on site available to assist in case of any issues.
Sep 20, 11:50 BST