** AT RISK ** Maintainance activity at Volta - London
Scheduled Maintenance Report for Clouvider
Completed
The works have been cancelled by the operator until they can better understand the chain of events that led to Saturday’s outage.

We will send a new notification once these works are re-scheduled.
Posted Feb 03, 2024 - 16:02 GMT
Scheduled
Volta will be performing a maintenance on their HV panels B. This has been notified to us as non-service affecting activity. All our equipment is dual fed and in case of any feeds being affected should continue working uninterrupted as normal.

Given the Saturday's incident during similar works by this operator, that affected both redundant feeds, we are communicating these planned works as ** AT RISK **.

As per the site:

04 February 2024. Sunday. Change of HV-B to Temporary ATS Panel. During this period, a qualified AP will be on hand to operate the engine generator system manually should engine generators be required.

Our team will be monitoring and responding to any issues.
Posted Feb 03, 2024 - 14:18 GMT