Planned works - switch software update - London Metro

Scheduled Maintenance Report for Clouvider

Completed

The scheduled maintenance has been completed.
Posted Aug 12, 2024 - 06:00 BST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 12, 2024 - 00:00 BST

Scheduled

Clouvider will be performing planned engineering works in London in order to update Juniper switch estate to the current JTAC recommended version.

The maintenance is essential for network security and in order to avoid unplanned outages in the future.

Window start date: 2024-08-12 00:00 BST
Window end date: 2024-08-12 06:00 BST
Window length: 6 hours
Expected downtime: up to 30 minutes

Only one switch will be worked at a time. Expected downtime per switch (and for the directly connected services) is up to 30 minutes. The works cannot be re-scheduled and individual services cannot be excluded from these planned works.

We will provide updates through our StatusPage during the works.

Many thanks for your patience during these essential works.
Posted Jul 26, 2024 - 11:41 BST
This scheduled maintenance affected: Customer Portal (Customer Portal, Service Management API), Datacentres (Docklands - London, UK, Enfield - London, UK, Cyxtera LHR1 - London, UK), Network (MPLS/VPLS Services, London, UK Core Network), Hosted Services (Anycast DNS, Web Hosting, Public Cloud, Private Cloud, Dedicated Servers), and Main Website.